FAST InPrO Project Plan

Project Plan

Input
Dynamic Work Breakdown Structure
Organization Breakdown Structure

Process
Create a task list and work breakdown structure (WBS)
Start by exporting your Dynamic Work Breakdown Structure to MS Project (supported by our tools) as your Summary Tasks. Add Sub Tasks as required.
Enter task durations or work estimates as discussed with the engineering teams.
Create dependencies between tasks.
Add tests and integration process into account.
Add management milestones, documentation, and reviews to your project plan,
Enter task durations or work estimates
Check for tasks, owner in charge, and risk assessment on the tasks on the critical pass.

More information in these links:
http://office.microsoft.com/en-us/project-help/create-a-project-plan-in-5-easy-steps-HA001136153.aspx
http://www.cops.usdoj.gov/html/cd_rom/inaction1/pubs/techguide/PartIIICreateaProjectPlan.pdf

Output
The output of this phase is a project plan SMART based. Each employee knows what he has to do, when, and how. The plan should have milestones to check if we are on track.

SMART - Specific, Measurable, Achievable, Realistic, and Time based

More WBS Planner Info links

Be preferred and get work without experience

Introduction

WBS Template using WBS Planner

Projects Methods using WBS Planner

Dynamic Work Breakdown Structure Insights

Overview

Product Breakdown Structure PBS

Cost Breakdown Structure CBS

Organization Breakdown Structure OBS

Stage Breakdown Structure SBS

Work Breakdown Structure WBS

Normalization of Work Breakdown Structure

Dynamic Work Breakdown Structure method

Dynamic Work Breakdown Methods

Recourse Allocation Matrix RAM

Portfolio Recourse Allocation Matrix PRAM

Functional Analysis Decomposition and Composition

Risk Evaluation

Alternative (design & performing)

Logistics Consideration

Tests Plans

Input Process Output (InPrO)

Project process

Requirements

System Requirements Specifications

System Concept

Detailed Design

Work Breakdown Structure

FAST InPrO Project Plan

Risk Management

Tracking and Control

Failure Handling

Executive Summary

Workshop: Methods and Tools 2 days